As of November 2026, Saudi Arabia’s newest airport is Red Sea International (opened September 2023), and the newest terminal is Jeddah’s Terminal 4 (phased opening from 27 September 2026). Four other terminals opened or reopened earlier in 2026: Riyadh Terminal 2, AlUla, Al-Jouf and Al-Wajh. Several bigger projects are being built but are not open: King Salman International Airport in Riyadh, the new Jazan airport and the Madinah expansion. New terminals at Abha, Taif and Qassim are still at tender stage, and NEOM International Airport has no published construction or opening date.
This page tracks 19 projects. Each one is labelled with one of four statuses (open, being built, in tender or design, announced with no date), and every date is the latest one we could find in an official release or in the press quoting one. Read it as a status board: a target year is not an opening date.
Where each project stands
- Open in 2026
Riyadh Terminal 2, AlUla, Al-Jouf, Al-Wajh and Jeddah Terminal 4. Red Sea International has been open since 2023.
Open in 2026 - Being built or contracted
King Salman International, the new Jazan airport and the Madinah expansion; Hail's terminal works were contracted in July 2026. No confirmed opening day.
Being built or contracted - In tender or design
Abha, Taif and Qassim public-private partnerships, Dammam's expansion design and Jeddah's next six packages.
In tender or design - Announced, no date
NEOM International, AlUla's second terminal, the Al-Baha expansion and a new Yanbu terminal.
Announced, no date
Saudi airport expansion plan: the 2030 targets
The projects all serve the Saudi Aviation Strategy run by the General Authority of Civil Aviation (GACA). As reported by MEED and Arab News in 2026, the strategy targets three things by 2030:
- 330 million passengers a year, against 140.9 million in 2025 (GASTAT);
- more than 250 destinations linked by air, against 176 in 2025;
- 4.5 million tonnes of air cargo a year.
The gap is large. Reaching 330 million from 140.9 million in five years means multiplying traffic by 2.34, or growing by about 18.5% every year from 2026 to 2030, by our calculation. Traffic grew by 9.6% in 2025, according to GASTAT. Most of the new capacity is therefore concentrated in Riyadh and Jeddah: King Salman International is designed for about 100 million passengers a year by 2030, and Jeddah’s operator targets more than 90 million by the same year.
Who builds what matters for timing. The four big airports are run by companies of Matarat Holding (Riyadh, Jeddah, Dammam) or by a concession (Madinah). Regional airports such as Abha, Taif, Qassim and Hail belong to Cluster2 Airports, and Matarat is tendering their new terminals as public-private partnerships (PPP) through the National Centre for Privatisation. A PPP adds a contract award stage before any construction, which is why those dates move more than the others.
Dated milestones, past and announced
-
Done
Red Sea International opensFirst Saudia flight from Riyadh on 21 September; first international flight in April 2024.
-
Done
Riyadh T2, AlUla, Al-JoufRiyadh's rebuilt Terminal 2 and AlUla's enlarged terminal open; Al-Jouf's new terminal is inaugurated on 19 January.
-
Done
Al-Wajh reopensFlights resume on 24 May after Red Sea Global's two-year upgrade.
-
Done
Jeddah Terminal 4Phased opening from 27 September; North Terminal airlines moved out by mid-October.
-
Now
New Jazan airport trialTrial operations targeted during 2026 at 94% completion (April). No date announced.
-
Next
Madinah expansionCapacity from 8 to 18 million passengers a year, per GACA.
-
Next
New Abha terminalCompletion target for phase one; contract not yet awarded in November 2026.
-
Next
King Salman InternationalFirst terminal reported for 2029 or 2030; no official date.
New airports and terminals that opened in 2026
Five terminals opened or reopened between January and September 2026. Together they add about 25 million passengers a year of design capacity, by our sum of the published figures (Jeddah Terminal 4 adds 15 million; the other four add the difference between old and new capacity).
| Project | Opened | Capacity (passengers a year) | What changed for travellers |
|---|---|---|---|
| Riyadh, King Khalid Terminal 2 | Late January 2026 | Terminals 1 and 2 together: 6M to 14M | Rebuilt terminal for Saudi airlines’ international flights |
| AlUla terminal expansion | 15 January 2026 | 400,000 to 700,000 | Passport counters rose from 4 to 12 |
| Al-Jouf new terminal | Inaugurated 19 January 2026; all flights from 25 February | About 175,000 to 1.6M | Old terminal closed; 24,000 m² building |
| Al-Wajh upgrade (Red Sea Global) | Flights resumed 24 May 2026 | 100,000 to 500,000 | Reopened after two years closed |
| Jeddah Terminal 4 | Phased from 27 September 2026 | Up to 15M | Foreign airlines moved from the North Terminal |
GACA put the cost of the Al-Jouf terminal at more than SAR 440 million. AlUla’s expansion is a stop-gap: in October 2023 the Royal Commission for AlUla unveiled a separate second terminal designed for 6 million passengers a year, with no opening date published since. Our Al-Jouf airport guide and AlUla airport guide cover the terminals as they work today.
Red Sea International (RSI), the only brand-new airport site of recent years, opened on 21 September 2023 with Saudia flights from Riyadh; its first international flight, from Dubai on flydubai, landed on 18 April 2024. It is planned for one million visitors a year by 2030, about two million passengers a year counting arrivals and departures.
Jeddah airport expansion project: Terminal 4 and the next phase
Terminal 4 is not a new building on a new site. It is the former South Terminal, opened in 1981 and closed to passengers in 2020, rebuilt to 97,000 m² with room for up to 15 million passengers a year and a group check-in area for Hajj and Umrah pilgrims. Wizz Air, AJet and SalamAir moved first on 27 September 2026, followed by Fly Jinnah, Nesma, Akasa Air, SyrianAir, Pegasus, Azerbaijan Airlines and Tunisair in the following week (Arab News). By 17 October 2026 the remaining North Terminal flights had moved to Terminal 4 or the Hajj and Umrah Terminal (Khaleej Times). Our Jeddah Terminal 4 guide lists the airlines and access.
More work is coming. MEED reported on 22 September 2026 that Jeddah Airports Company will tender six packages over two years:
- airfield rehabilitation (third quarter of 2026);
- a five-year construction framework (fourth quarter of 2026);
- a Terminal 3A package (first quarter of 2027);
- a fuel farm (second quarter of 2027);
- Terminal 1 optimisation (fourth quarter of 2027);
- Concourse C works (second quarter of 2028).
These are tender dates, not opening dates. The airport’s targets also differ by source: the operator now speaks of more than 90 million passengers a year by 2030, while the 2023 master plan reported by MEED gave 114 million a year by 2031 for about SAR 115 billion. Jeddah handled about 53.5 million passengers in 2025 (GASTAT). For which airline uses which building today, check the Jeddah departures board.
Good to know: the airport code stays JED whichever terminal you use. When an airline email mentions a “new terminal” in Jeddah since 27 September 2026, it means Terminal 4, so read the terminal on your booking rather than the code.
Riyadh airport new terminal and King Salman International Airport
Riyadh has two separate projects, and they are often confused.
King Khalid International (RUH), the airport in use. Prince Faisal bin Bandar, Emir of Riyadh, inaugurated the rebuilt Terminal 2 in late January 2026. GACA’s president said Terminals 1 and 2 together could now handle 14 million passengers a year, against 6 million before (Gulf News, 26 January 2026). The terminal reallocation that followed was completed between 16 and 25 February 2026. Under temporary operating changes since October 2026, only Terminals 1 and 2 are in use, so check your terminal with your airline; our Riyadh airport guide is kept current.
King Salman International Airport (KSIA), the future airport. It is being built around and north of King Khalid International. The developer’s official site gives these figures:
- about 57 km² in total, of which 45 km² of airport land and 12 km² of real estate;
- six runways and six terminals, plus a royal terminal and a private aviation terminal;
- about 100 million passengers and 2 million tonnes of cargo a year by 2030;
- 185 million passengers and 3.5 million tonnes of cargo a year by 2050.
Work under way, as of November 2026: construction of a third runway began at the end of December 2025 (KSIA), and initial landside works for the private aviation apron were complete by May 2026 (MEED). Three contractor teams finished an early contractor involvement phase for Terminal 6 in October 2026 and were preparing bids for the main construction contract in early November (MEED). The main contract had been targeted for award by mid-2026.
No official opening date exists. Gulf News reported a 2029 target and Argaam, quoting the acting chief executive, 2030. The full picture is on our King Salman International Airport page.
Madinah airport expansion project
Prince Mohammad bin Abdulaziz International Airport is the clearest case of an airport running beyond its design. It was built for 8 million passengers a year and handled about 11.8 million in 2025 (reports give 11.7 and 11.9 million); GACA put its utilisation above 137% of design capacity. Abdulaziz Al-Duailej, president of GACA, said at the Hajj Conference in November 2026 that the expansion will raise capacity to 18 million passengers a year and be completed in October 2027 (Saudi Gazette, 9 November 2026; CAPA, 10 November 2026).
The target has moved slightly: a GACA release of March 2024 spoke of 17 million passengers by the end of 2027. The airport stays open during the works. Practical details on terminals and transport to the Prophet’s Mosque are in our Madinah airport guide.
Dammam airport expansion project
King Fahd International Airport is at the design stage. Dammam Airports Company signed a design contract with WSP, reported on 14 September 2026, covering terminal expansion, entrances and access roads, baggage systems, digital services and signage (Arab News). The master plan, unveiled in July 2025, targets:
- more than 19.3 million passengers a year by 2030 (13.7 million in 2025);
- 32 million passengers a year in the long term;
- more than 600,000 tonnes of cargo and 77 aircraft movements an hour.
No construction start or completion date had been published by November 2026. The Dammam airport guide covers the terminal as it works today.
Jizan new airport opening date
The new King Abdullah bin Abdulaziz International Airport is the most advanced regional project, but it has no opening date. It is being built at al-Sabkha, about 30 km north of Jazan city, and will replace the current airport, which is about 3 km from the centre (3.4 km by road, by our calculation). When the project was announced in March 2013, Arab News reported that the current airport would close once the new one opens.
Progress reported in the Saudi press, quoting the emirate and the Saudi Press Agency:
| Date reported | Completion | Source |
|---|---|---|
| End of December 2024 | 70% | Al Watan |
| November 2025 | 87% | Al Watan (25 December 2025) |
| January 2026 | 92% | Okaz (15 January 2026) |
| April 2026 | 94% | SPA, via Al-Jazirah (30 April 2026) |
The figures describe a 57,000 m² terminal with 12 gates, 10 boarding bridges, 32 check-in counters and about 2,000 parking spaces, sized for 5.4 million passengers a year in its first phase. The current airport was designed for 900,000 passengers a year but handled about 2.84 million in 2019, or 315% of its design, by our calculation from Saudipedia figures. The emir asked for regular progress meetings ahead of trial operations targeted during 2026. We found no announcement of a transfer date as of 19 November 2026. Our Jazan airport guide will show the switch when it is announced.
Watch out: a completion percentage is not an opening date. Do not book a transfer or a hire car for the new Jazan airport until the operator announces the first day of flights there.
Jazan: today's airport and the new one
Current airport
- Distance to city
- About 3 km
- Design capacity
- 900,000 a year
- Gates
- 3 domestic, 1 international
- Status
- All flights
New airport
- Distance to city
- About 30 km north
- Design capacity
- 5.4 million a year
- Gates
- 12, with 10 boarding bridges
- Status
- 94% built (Apr 2026)
Keep planning on the current airport until a transfer date is announced.
Abha airport expansion project
A new terminal for Abha was announced on 12 October 2023, with a design by Foster + Partners inspired by the stone villages of Asir. The figures, from Saudipedia and MEED:
- terminal area from about 10,500 m² to 65,000 m² in the first phase;
- capacity from about 1.5 million to more than 13 million passengers a year, and from 30,000 to more than 90,000 flights;
- 20 gates and 41 check-in counters, a new apron and a rapid-exit taxiway;
- completion targeted for 2028.
The existing terminal served 4.4 million passengers in 2019 (MEED), almost three times its 1.5 million design capacity. It will close once the new terminal is working. The project is a 30-year build-transfer-operate contract. Four groups were in the final round, and MEED reported on 10 February 2026 that the award would come “within a few weeks”. A report published on 12 November 2026 still described the process as at an advanced stage, with no winner named. Until a contract is signed, treat 2028 as a target. Flights, the flynas base and transport are in our Abha airport guide.
Good to know: the jump is bigger than the passenger figures suggest. Cluster2’s winter 2026 capacity declaration lists 5 domestic and 2 international gates at today’s terminal, against 20 gates planned in the new one.
New Taif International Airport project
Taif is getting a new airport on a new site, about 21 km south-east of the current one. MEED (7 July 2026) and Zawya give the scope: one runway with a full-length parallel taxiway, a passenger terminal, one commercial apron, car parks and access roads, sized for 2.5 million passengers a year by 2030, with room to grow to meet demand up to 2055. MEED describes it as serving Taif, its surrounding area and Umrah pilgrims. The current airport is about 113 km by road from the Masjid al-Haram in Makkah, by our calculation.
The timeline so far:
- 2017: GACA awarded the project to a consortium of Consolidated Contractors Company, Munich Airport International and Asyad; it stalled when the sector was restructured (MEED).
- January 2026: five bidders prequalified for the new tender.
- June 2026: request for proposals launched by Matarat and the National Centre for Privatisation.
- 24 July 2026: bid deadline (MEED).
No award had been reported by 19 November 2026. The current airport and its two terminals stay in use; see our Taif airport guide.
Qassim, Hail and other regional airport projects
The other regional projects are at very different stages:
| Airport | Status, November 2026 | Key figures |
|---|---|---|
| Qassim (ELQ) | Tender: six groups qualified (MEED, 7 September 2026) | New terminal plus runway, taxiway and apron works, 30-year contract |
| Hail (HAS) | Works contract won by Safari Group (July 2026) | 5,600 m² southern extension, about 1.7M passengers a year by 2030 |
| Al-Baha (ABT) | Expansion described, no date | 20,310 m² passenger hall, four bridges, 1M passengers a year (Saudipedia) |
| Yanbu (YNB) | 2017 concession to TAV and Al Rajhi stalled; no new date | Master plan being updated by Sener |
| Tabuk (TUU) | Master plan being updated by Sener; no project announced | 1.79M passengers in 2019 on a 1.5M design (Saudipedia) |
Qassim drew 89 expressions of interest in early 2026 before the shortlist. The 2017 award covering Yanbu, Qassim and Hail to TAV Airports and Al Rajhi Holding stalled after the aviation sector was restructured, MEED reported, which explains why Qassim and Hail are being procured again. Our Qassim airport guide and Hail airport guide describe the current terminals.
NEOM airport and the Red Sea airports
Two different NEOM airports appear in searches. NEOM Bay Airport (NUM) is open, with Saudia flights to Jeddah and Riyadh, flyadeal to Riyadh and Dammam and flydubai to Dubai, as listed in NEOM’s July 2026 airport FAQ and our route data of 15 November 2026. NEOM International Airport is a planned airport: AECOM announced on 22 March 2023 that it had been appointed project management consultant, covering master planning through to opening. No construction milestone or opening date has been published since, and Semafor reported in May 2026 that wider NEOM work had been reorganised. Flights to the area today are in our NEOM Bay airport guide.
Further south, Red Sea Global’s two airports are both open. Red Sea International Airport serves the resorts of The Red Sea, and Al-Wajh, reopened in May 2026, is the gateway Red Sea Global gives for the AMAALA resorts.
What the new airports change for your trip
| If you are flying to… | What changes | What to do |
|---|---|---|
| Jeddah, on a foreign airline | Many airlines left the North Terminal for Terminal 4 or the Hajj and Umrah Terminal in Sept-Oct 2026 | Read the terminal on your booking and the airline’s notice |
| Riyadh | Terminal use differs from the 2026 allocation under temporary operating changes | Confirm with your airline; King Salman International has no flights |
| Jazan, after the switch | Airport about 30 km north instead of about 3 km from the centre | Plan a longer transfer; check the airport’s announcement |
| Abha, Taif, Qassim | Nothing yet: tenders are not awarded | Use the current terminals |
| Madinah | Works until October 2027 | Allow extra time in peak Umrah and Hajj periods |
| Al-Jouf, AlUla, Al-Wajh | New or enlarged terminals already in use | Old guides and photos may show the previous building |
Our route data, read from airline route tables on 15 November 2026, shows how many destinations each project will affect when it opens: about 37 from Madinah, 25 from Abha, 23 from Qassim, 15 from Taif, 11 from Jazan and 8 from Hail. When an airport moves to a new site, every one of those routes moves with it, usually overnight.
Before you fly to an airport with a project under way
Tick as you go: saved on this device onlyHow we checked this page
We read the official site of King Salman International Airport and releases from airport operators and GACA as quoted by the Saudi Press Agency. Project stages, bidders and tender dates come from MEED and the Saudi and Gulf business press (Arab News, Saudi Gazette, Okaz, Al Watan, Al-Jazirah, TradeArabia, Gulf News), checked against each other between 15 and 19 November 2026. Passenger totals are GASTAT figures for 2025. Distances and route counts come from our own calculations on OpenStreetMap data and on Wikipedia route tables read on 15 November 2026. Where sources disagree, both figures are given. Where no date has been announced, the page says so.
Questions travellers ask
When will the new Jizan airport open?
No opening date has been announced. The Saudi Press Agency reported the new King Abdullah bin Abdulaziz International Airport at about 94% complete in April 2026, with trial operations targeted during 2026. Until the airport announces a transfer date, all Jazan flights use the current airport about 3 km from the city.
What is the Abha airport expansion project?
It is a new terminal of 65,000 m² for more than 13 million passengers a year, against about 1.5 million today, to be built and run by a private partner on a 30-year contract. MEED reported in February 2026 that the award was weeks away, but no award had been announced when we last checked (November 2026). Completion has been targeted for 2028.
What is the new Taif International Airport project?
A new airport about 21 km south-east of the current one, sized for 2.5 million passengers a year by 2030. Matarat and the National Centre for Privatisation tendered it as a 30-year build-transfer-operate contract, with bids due on 24 July 2026. No award or opening date had been announced by November 2026.
Does King Khalid International Airport have a new terminal?
Terminal 2 reopened in late January 2026 after a full rebuild, and with Terminal 1 it raised capacity from 6 to 14 million passengers a year, according to GACA. Under temporary operating changes since October 2026, check your terminal with your airline. The much larger King Salman International Airport is under construction next door and is not open.
Is NEOM airport open?
NEOM Bay Airport (NUM) is open, with scheduled domestic flights and a flydubai service to Dubai. NEOM International Airport is a separate project: AECOM was appointed project manager in March 2023, but no construction milestone or opening date has been published since.
What is the Jeddah airport expansion project?
Terminal 4, the rebuilt former South Terminal, opened in phases from 27 September 2026 with capacity for up to 15 million passengers a year. MEED reported in September 2026 that Jeddah Airports Company will tender six more packages until 2028, including Terminal 1 optimisation and a new Concourse C. The operator's target is more than 90 million passengers a year by 2030.
When will the Madinah airport expansion be finished?
GACA's president said in November 2026 that the expansion will be completed in October 2027 and raise capacity from 8 to 18 million passengers a year. The airport handled about 11.8 million passengers in 2025, well above its design capacity: GACA put its utilisation above 137%.
What is the biggest new airport in Saudi Arabia?
King Salman International Airport in Riyadh, planned over about 57 km² with six runways and about 100 million passengers a year by 2030, rising to 185 million by 2050. It is under construction and not open. Reports give 2029 or 2030 for the first terminal, and no official date has been announced.